Showing posts with label safety analysis. Show all posts
Showing posts with label safety analysis. Show all posts

Tuesday, June 19, 2007

NRC Smacks Entergy's License Renewal Application


Great news folks...Indian Point just hit a MAJOR snag in the process to relicense their aging, failing reactors. Seems that the NRC has found some crucial OMMISSIONS in the application...OH GEE, like that is a big surprise. More importantly, these are issues we now know to make contentions on...trust me, they left those items out for a reason, not because it was a clerical oversight.

June 18, 2007

Mr. Michael Kansler
President
Entergy Nuclear Operations, Inc.
440 Hamilton Avenue
White Plains, NY 10601

SUBJECT: REVIEW STATUS OF THE LICENSE RENEWAL APPLICATION FOR THE
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3

Dear Mr. Kansler:

By letter dated April 23, 2007, as supplemented by letter dated May 3, 2007, Entergy Nuclear Operations, Inc. (Entergy) submitted an application for renewal of Operating Licenses Nos. DPR-26 and DPR-64 for the Indian Point Nuclear Generating Unit Nos. 2 and 3, respectively.

By teleconference on June 6, 2007, U.S. Nuclear Regulatory Commission (NRC) staff informed representatives from Entergy that certain information is needed for the staff to complete the acceptance review of the license renewal application (LRA) for the Indian Point Nuclear Generating Unit Nos. 2 and 3. Specifically, the NRC staff informed Entergy that the current licensing basis for Unit 2 was not fully represented in accordance with Part 54.4(a)(3) of Title 10 of the Code of Federal Regulations (10 CFR 54.4(a)(3)).

During its acceptance review, the NRC staff determined that the applicant has not included within the scope of license renewal those systems, structures, and components relied on in the safety analyses or plant evaluations to perform a function that demonstrates compliance with the requirements for station blackout (SBO) per 10 CFR 50.63, and safe shutdown per 10 CFR 50.48. In this regard, the LRA did not include information on the gas turbines currently credited as an alternate power supply for the Appendix R and SBO events.

Please respond within 14 days of the receipt of this letter to inform the staff of your plans to resolve the acceptance issue identified above. If you have any questions on this matter, please contact Bo Pham by telephone at 301-415-8450 or via e-mail at BMP@nrc.gov.

Sincerely,


Pao-Tsin Kuo, Director
Division of License Renewal
Office of Nuclear Reactor Regulation
Docket Nos. 50-247 and 50-286
cc: See next page